Work on the first of the north buildings in the project (Phase 2) has commenced. Excavation is complete on Building D and the crew is prepping to pour the foundation. This second phase of buildings will feature an inverted layout with the living spaces on the top floor.


Progress continues on the southern buildings with Building G nearing completion. Ceiling fans have been hanged and the exterior railings are in place. Installation of interior railings has started. Floor installation continues in Building E. The trim carpenters are hard at work in Building C and the cabinets are in place in Building A.


Looking to visit Crested Butte this summer? Be sure to schedule a private tour while you are in town!




 
 
 

Excavators are back on site this week working on the main road into the site as well as the driveways to each of the buildings. Once the roadways are complete, they will break ground on the first buildings in Phase 2 of the project, Buildings D and F.


Building G saw some detail work start with the installation of the door hardware, shower benches and trim, and light fixtures. Ceiling fans have been delivered and will be installed next week. Countertops have been installed in Building E along with tile backsplashes. Trim and door installation continues in Building C. Drywall inspections have passed in Building A. Painters are finishing up the first round of paint and cabinets are being placed. Bathroom tile has also started in Building A.


If you are planning a trip to Crested Butte, be sure to call and schedule a private tour!



 
 
 

It has been an exciting two weeks at the Brush Creek Village site with Building G getting closer and closer to completion. One garage door has been installed with the remaining two scheduled to go in later this month. The electrical trim out has also started and the appliances have been delivered and installed. The flooring for the stairs is in place in two of the three units. Cabinets, flooring, and bathroom tile are being installed in Building E. Building C has balcony railings in place. Interior doors and trim are in process, and the plumbing trim out has also started. The drywall and painting crews continue work on Building A. Stay tuned for additional details!


Planning a visit to Crested Butte? Call to schedule a private tour!



 
 
 