Despite some rainy weather last week, our various teams continue to make progress towards completion. The landscapers have completed the installation of the individual sprinkler systems and trees have been planted. Fireplace surrounds and interior railings are in place in Building G. Final inspections are being scheduled for Building G with Certificates of Occupancy anticipated by the end of the month. Flooring is complete in Building E and the plumbing trim out has commenced. Trim and interior door installation continues in Building C and the electrical trim out is underway. Countertops have been measured for Building A and the plumbing trim out has started.
The HOA documents are complete and copies have been posted on the Location page of our site. The association will be managed by Toad Property Management.