Phase 2 is underway

Work on the first of the north buildings in the project (Phase 2) has commenced. Excavation is complete on Building D and the crew is prepping to pour the foundation. This second phase of buildings will feature an inverted layout with the living spaces on the top floor.


Progress continues on the southern buildings with Building G nearing completion. Ceiling fans have been hanged and the exterior railings are in place. Installation of interior railings has started. Floor installation continues in Building E. The trim carpenters are hard at work in Building C and the cabinets are in place in Building A.