And Phase 2 is coming along nicely! All units in Phase 1 have obtained their Certificates of Occupancy and the remaining two units (103 & 109) are undergoing outstanding punchlist items in preparation for their final cleans. It has been exciting to watch new owners settling in and enjoying the community.
The first two buildings of Phase 2, Buildings D and F, are well underway. Building D has all drywall in place, and painters are on site following the drywallers as they wrap up texturing. Building F has been roughed in with both plumbing and electrical, and insulation is being installed. Despite that last round of snow, the various teams have been able to maintain a solid pace as they work toward completion.
Did you miss out on a 4-bedroom unit in Phase 1? Do not stress as Phase 2 units will be available this summer. Reach out to schedule a tour and see the amazing views of the Butte!