Stair treads and garage doors

The cool weather has returned with a week long storm cycle making the whole valley greener (and happier!). Stair treads have been installed in Building C, bringing it one step closer to completion. Interior railings are being fabricated and will be installed at the start of next week along with the fireplace surrounds and shower glass doors. Once the railings are in place, final inspections for the Certificates of Occupancy will be scheduled. Garage door installation commenced in Building E and bathrooms have been measured for shower door glass. Flooring installation in Building A will be finished next week and the trim carpenters will follow to install trim and hang doors.


Planning a visit to see the upcoming fall colors? Reach out to schedule a private tour!