More CO's and final roofing

As we settle into off-season, the weather remains relatively warm throughout the day. With the sunny days, our crews continue to make progress on the remaining two buildings, B & H. Buildings D & F are complete, with certificates of occupancy in hand. The final delivery of siding has arrived, which will be one of the finishing touches on the exteriors of Buildings B & H. The last of the roofing has been installed on Building H, making all buildings ready for the upcoming snowy weather. Paint crews have finished the first coat of paint in Building B and the plumbers are on site hanging boilers. Insulation is complete in Building H and the drywallers are scheduled.


It is not too late to secure a unit prior to the ski season. Reach out to learn more about the possibilities!



 
 
 