The entire project is looking more complete as grass seed was installed behind Buildings G & E. Weather permitting, the landscapers will return tomorrow to seed behind Buildings C & A. Building G has passed all its final inspections and shower glass is scheduled to go in this week along with other outstanding final touches (mirrors, toilet paper holders, and towel hooks). Garage doors are tentatively scheduled to be installed in Building E next week. Trim has also been painted in Building E and interior railings are being installed. Final plumbing and electrical inspections are being scheduled for Building C and all units will be measured for shower glass this week. The tile crew is back on site to install kitchen backsplashes in Building A and the electrical trim out is underway.