As we get ready to celebrate the New Year, we are starting to see some exciting progress, primarily with the flooring. Installation began in Building G this week and the crew is making swift progress. Doors and other trim elements have been delivered and installation will commence once the flooring is finished. The siding team continues to work hard despite the cold weather with one building almost complete and they will be starting Building C after the holiday. Buildings A and E continue to see forward motion as plumbing and electrical rough-ins are being wrapped up and inspected, paving the way for the insulation and drywall crews to follow.