It has been an exciting two weeks at Brush Creek Village! Certificates of occupancy of have been issued for Building E and more units have gone under contract leaving only 3 units available in Phase 1. Finishing touches are taking place in Building E and we will be scheduling final cleans soon. Building G is about 2 weeks out from final inspections. The remaining garage doors will be installed next week. Interior railing installation will wrap up the final week of month. Shower glass is being fabricated and the painters are on site working on final touch ups.
It is not too late to see the project. Schedule your tour today!