Building G is complete

Our entire team is overjoyed to announce that Building G is complete. The finishing touches (shower doors, mirrors, toilet paper holders, and towel hooks) have been installed and Certificates of Occupancy have been provided. Building C is following closely and all units have already passed final plumbing and electrical inspections. Stair treads arrived this week and once in place, interior railings can be installed. Appliances were delivered to Building E this week and installation is underway. The tile crew is back at work in Building A and the flooring installation continues. The landscapers continue to work on the last of the trees and other planting. Remaining work on the roadway is in process.