Appliances are in!
- cgates304
- Jul 22
- 1 min read
Things are starting to look more polished around Building D with the recent arrival and installation of all the appliances and the fireplace surrounds. All Phase 2 units feature a wine cooler, offering additional beverage storage. Stair treads are scheduled to go in this week and shower glass will be installed as soon as it is out of production. If you haven't seen the updated kitchen layout for the 3-bedroom units, be sure to take a look!
Light fixtures are in place in Building F and the tile crew is on site working through the bathrooms. Railings are also being installed in Building F. Framers continue to work diligently on Buildings B and H. Building H now has windows and doors, and Building B is prepped for roofing. Rough ins are also underway in Building B. As well, we are excited to announce that paving of all driveways and the main roadway will commence in September 2025.