Final touchups and inspections

Updated: Jul 17, 2024

The continuing rainy weather is making the wildflowers happy and keeping us safe from wildfires. Our crews are excited to announce that Building G has passed its final plumbing and electrical inspections as well as air tests. Remaining inspections are being scheduled to obtain our Certificates of Occupancy. Large strides are being made in Building E with plumbing trim out complete and the electrical trim out in process. Appliances for Building C were delivered and are in the process of being installed. The units are also being prepped for final paint. Countertops have been installed in Building A and work on the plumbing continues.